Proposed Timeline

Phase 1: Skyline Reconstruction, Solana Highlands Modernization, solar and energy storage system at Solana Pacific
Phase 2: Solana Vista Reconstruction and Solana Santa Fe Modernization
Phase 3: Modernization of Carmel Creek and Improvements to Solana Pacific and Solana Ranch
 
2015-16 School Year
  • Winter 2015-16
    • Phase 1: Planning for Skyline Reconstruction and Solana Highlands Modernization
2016-17 School Year
  • Fall 2016
    • Phase 1: Plans submitted to state
    • Election
  • Spring 2017
    • Phase 1: Plans approved by state
    • First issuance of bonds
  • June 2017
    • Phase 1: Break ground/Demolition

2017-18 School Year

  • Phase 1: Skyline Construction (Solana Highlands modernization and Solana Pacific solar completed in summer/early fall 2017)
  • Phase 2: Planning for Solana Vista Reconstruction and Solana Santa Fe Modernization
2018-19 School Year
  • Fall 2018
    • Phase 1: New Skyline facility ready for occupancy
    • Phase 2: Plans submitted to state
  • Spring 2019
    • Phase 2: Plans approved by state
    • Second issuance of bonds
  • June 2019
    • Phase 2: Break ground/Demolition

2019-20 School Year

  • Phase 2: Construction
  • Phase 3: Planning for Carmel Creek Modernization and Improvements to Solana Pacific and Solana Ranch

2020-21 School Year

  • Fall 2020
    • Phase 2: New Solana Vista facility ready for occupancy
    • Phase 3: Construction begins